The aim of this project is to bring electricity to the village that was existed before the war. In 1991 there were 21 houses connected to the power grid, together with the neighboring Radeke village.
Currently, there are the seven formal requests for the connection to the power gird which are duly handed over to the HEP Group who formally doesn’t respond to these demands because they considered them as unprofitable, citing the profitability of investments.
Our aim was to put together all owners of the houses in the Lončari village and Radeke village and to make an unique request for the connection to the power gird and in this way justify the return on investment.
In 2019 the Lončari village and Radeke village are again connected to the electricity after 23 years of darkness.
Thanks to anyone that helped this process!